All accounts now require passwords. Please click HERE for more details.
Library Hours: Monday-Thursday 9:30am-7:30pm, Friday-Saturday 9:30am-5:00pm and Sunday 12pm-5pm
Public computer use is limited to one 2 hour computer session daily.

Archive Search Results


Showing 81 - 100 of 433 , query time: 0.01s
Thumbnail for 'Placing concrete in spiral stairway and air shafts'
Format:
Image
Placing concrete in spiral stairway and air shaft from elevation 7641 to 7649.5.
Thumbnail for 'Reinforcing spiral stairway and air shaft'
Format:
Image
Placing reinforcement in spiral stairway and air shaft.
Thumbnail for 'Dome of gate chamber'
Format:
Image
Dome of gate chamber and base of stair shaft after forms were stripped.
Thumbnail for 'Looking downstream in spillway (2)'
Format:
Image
Looking downstream in spillway channel from sta. 14+25. Excavation in foreground is too subgrade. Water appears to have been trapped by rock ridge seen in Pine R - 149.
Thumbnail for 'Looking upstream at spillway excavation (left)'
Format:
Image
Looking upstream at excavation for spillway stilling basin. Taken from right side of spillway at sta. 30+50.
Thumbnail for 'Looking upstream at spillway excavation (right)'
Format:
Image
Looking upstream at excavation for spillway stilling basin. Taken from right side of spillway at sta. 30+50.
Thumbnail for 'Looking upstream in spillway (1)'
Format:
Image
Looking upstream in spillway channel excavation. Shovel is working in stilling basin.
Thumbnail for 'Looking downstream in spillway (5)'
Format:
Image
Looking downstream in spillway channel from sta. 7+00. Le Tourneau in foreground is excavating material upstream from sta. 15+00. Placing of concrete walls can be seen below station 15+00.
Thumbnail for 'Placing riprap next to spillway channel (2)'
Format:
Image
Placing dumped riprap on right side of spillway outlet channel. Darker colored rock was placed during 1939 season.
Thumbnail for 'Panorama of spillway and river channels (right)'
Format:
Image
Panorama looking upstream at spillway and river channels from spillway station 30+50. Placing of drains and fine grading for concrete on vertical curve and stilling basin floor can be seen at left.
Thumbnail for 'Looking upstream at spillway stilling basin (2)'
Format:
Image
Looking upstream at spillway stilling basin from right side of channel at station 30+50. Backfill behind stilling basin walls has been completed. Refer to Pine R - 306
Thumbnail for 'Looking downstream at spillway stilling basin'
Format:
Image
Looking downstream at spillway stilling basin from left side of channel at sta. 26+30. Placing section of stilling basin wall in foreground. Refer to Pine R - 283.
Thumbnail for 'Panorama of spillway and river channels (left)'
Format:
Image
Panorama looking upstream at spillway and river channels from spillway station 30+50. Placing of drains and fine grading for concrete on vertical curve and stilling basin floor can be seen at left.
Thumbnail for 'Looking upstream at spillway'
Format:
Image
Looking upstream at spillway from a point approximately 300 ft. downstream from end of structure. Discharge is estimated at 120-second feet.
Thumbnail for 'Looking upstream in outlet conduit (1)'
Format:
Image
Looking upstream in outlet conduit from point opposite sta. 13+40 of the outlet conduit. Dragline is placing concrete in invert with a bottom-dump bucket.
Thumbnail for 'Placing concrete in outlet conduit'
Format:
Image
Placing concrete in outlet conduit between stations 10+64.17 and 10+96.83. Dump trucks haul concrete from the mixing plant and dump into the hopper which is lowered to the buggy deck with a small dragline.
Thumbnail for 'Looking upstream in outlet conduit (2)'
Format:
Image
Looking upstream in outlet conduit from a point on the right rim near the intersection with the cut-off trench.
Thumbnail for 'Looking downstream in outlet channel'
Format:
Image
Looking downstream in outlet channel from sta. 14+50, showing construction of drainage system under the channel floor. Spillway cut is seen in background.
Thumbnail for 'Looking upstream in outlet channel (2)'
Format:
Image
Looking upstream in outlet channel from station 15+50 of spillway. Intersection of outlet channel and spillway in immediate foreground. Refer to Pine R - 166
Thumbnail for 'The dam claims a bulldozer'
Format:
Image
Caterpillar RD-8 bulldozer bogged down in excavation for the outlet works at station 13+40.