Thumbnail for 'Looking downstream in outlet conduit (2)'
Format:
Image
Looking downstream in outlet conduit from sta. 6+75. Concrete has been placed in the invert of the trashrack and transition.
Thumbnail for 'Excavation for outlet conduit'
Format:
Image
Excavation for outlet conduit, looking downstream from station 6+00. Bulldozer in foreground is cleaning off bedrock.
Thumbnail for 'Rock excavation for trashrack structure'
Format:
Image
Rock excavation for trashrack structure. Taken from point on rim to left of structure.
Thumbnail for 'Looking downstream in outlet conduit (3)'
Format:
Image
Looking downstream in outlet conduit from sta. 6+75. Two sections of the arch have been placed. Dragline is placing concrete in invert with bottom dump bucket. See Pine R - 74.
Thumbnail for 'Looking downstream in outlet conduit (4)'
Format:
Image
Looking downstream in outlet conduit from station 6+75. Refer to Pine R - 61, 69, 74, & 88.
Thumbnail for 'Looking downstream in outlet conduit (5)'
Format:
Image
Looking downstream in outlet conduit from station 6+75. Refer to Pine R - 61, 69, 74, & 97
Thumbnail for 'Le Tourneau loading with aid of a pusher'
Format:
Image
Le Tourneau loading with aid of a pusher in embankment material being removed for additional cut-off trench.
Thumbnail for 'Cross-section of embankment'
Format:
Image
Downstream face of cut for additional cut-off trench at station 18+00, showing cross-section of embankment placed during 1938, and the source of each type of material.
Thumbnail for 'Excavation of additional cut-off trench (4)'
Format:
Image
Excavating additional cut-off trench through embankment placed in 1938. Taken from point 25 feet upstream from dam axis at station 17+00.
Thumbnail for 'Upstream face of cut for additional trench'
Format:
Image
Looking at upstream face of cut for additional cut-off trench at sta. 17+50.
Thumbnail for 'Placing gate chamber, air shaft, & spiral stairway forms'
Format:
Image
Placing forms for outlet works gate chamber, air shaft, and spiral stairway shaft.
Thumbnail for 'Gate chamber taking shape'
Format:
Image
Inside forms and reinforcement in place for outlet works gate chamber and spiral stairway addition
Thumbnail for 'Looking downstream in outlet works'
Format:
Image
Looking downstream in outlet works. Placing inside forms for gate chamber. Hand-tamping embankment over conduit seen in foreground.
Thumbnail for 'View of left abutment from bottom of cut-off trench (2)'
Format:
Image
Looking toward left abutment in bottom of cut-off trench from point opposite axis sta. 9+00. Note drainage system at left side of trench has been covered with tar paper preparatory to placing embankment. Grout pipes can be seen extending up the side of the trench for grouting the system.
Thumbnail for 'View of river channel from bottom of cut-off trench'
Format:
Image
Looking toward river channel in bottom of cut-off trench on left abutment, showing foundation drainage installation. Drains will carry water to a corrugated metal pipe sump set in a concrete box. Water is being pumped from temporary sump at extreme left during installation.
Thumbnail for 'View of left abutment from bottom of cut-off trench (3)'
Format:
Image
Same view as Pine R - 157 after placing of embankment had started. Note mechanical tamping operations along contact at left side and around pump sump.
Thumbnail for 'View of left abutment along cut-off trench centerline (3)'
Format:
Image
Looking toward left abutment in cut-off trench from axis at sta. 9+00. End of concrete cut-off wall is seen in center.
Thumbnail for 'Le Tourneaus beginning additional cut-off trench excavation'
Format:
Image
Looking toward left abutment from axis sta. 20+00. Le Tourneaus are starting excavation for the additional cut-off trench in the foreground.
Thumbnail for 'Foundation drainage system'
Format:
Image
Foundation drainage system. Note grout risers at right side of trench for grouting system after embankment has been placed.
Thumbnail for 'Looking upstream at sump'
Format:
Image
Looking upstream at sump for foundation system from station 8+00.